A blower door test measures how leaky a space is. In a multifamily building we test single units, groups of units or the whole building. We also measure how much air passes between neighboring units. You get a written report with the numbers, the method and a list of leaks to fix if a unit fails. Coming soon: we are adding code compliance testing, and getting the certifications now. Tell us about your project and we will tell you where we are.

Illustration

01What it includes

Tests for the unit, the floor and the whole building

  1. 01

    Unit enclosure test

    A fan is sealed into the unit's door. It pulls the air pressure down to 50 pascals (a light, steady push), and we record how much air the fan moves to hold it there. That number, divided by the unit's enclosure area, is the result.

  2. 02

    Compartmentalization

    In an apartment building, air leaks through shared walls, floors and shafts as well as to the outdoors. Compartmentalization looks at how well each unit is sealed off from its neighbors.

  3. 03

    Guarded testing

    In a guarded test, neighboring spaces are held at the same pressure as the unit being tested. Then little air crosses the shared surfaces, and the reading shows leakage to the outdoors.

  4. 04

    Leak finding

    While the fan runs, we trace leaks with an infrared camera and by hand. Common trouble spots are outlets, plumbing and wiring penetrations, rim areas and shaft openings.

  5. 05

    Written report

    Each test is logged with the address, unit, date, tester, test method, enclosure area and result, so the file is complete and easy to check.

02The standard

What Fort Collins requires in multifamily buildings

Pass numbers come from the jurisdiction that adopted the code. Fort Collins publishes a protocol for stacked units. Check the number for your city or county before you schedule.

RequirementValueNotes and source
Maximum leakage per unit0.27 cfm50 per sq ft of unit enclosure areaThat is cubic feet per minute of air at 50 pascals, per square foot of the unit's walls, floor and ceiling. It applies to stacked units. It does not apply to duplexes, townhomes or rowhouses.Source: City of Fort Collins, multifamily air tightness testing protocol, checked Nov 16, 2026
Sampling in buildings with eight or more unitsTest seven units or 20 percent of units, whichever is greaterFor smaller buildings, read the full protocol or ask the building department.Source: City of Fort Collins, multifamily air tightness testing protocol, checked Nov 16, 2026
Test methods the protocol allowsANSI/RESNET/ICC 380, ASTM E779, ASTM E1827 or ASTM E3158These are the written procedures that say how to set up the fan, take readings and report them.Source: City of Fort Collins, multifamily air tightness testing protocol, checked Nov 16, 2026

Other cities and counties set their own numbers.

03How it works

Planning a multifamily test day

  1. Confirm the rule

    We check which standard and pass number apply to your project and who must receive the report.

  2. Pick the units

    We build a sampling plan from your unit list. On large buildings we usually test about 10% of the units, with a sample of each unit type. Some programs require a blower door on every unit at the same time. Others let us test one unit.

  3. Prepare the units

    Doors and windows closed, mechanical equipment set for the test, and the air handler and exhaust fans off. We send a short checklist for crews and residents.

  4. Report and retest

    We send results fast so a failed unit can be sealed and tested again. The plan says what happens next, based on your protocol.

What you receive

  • Test results for each unit, with the enclosure area
  • The test method and equipment used
  • A pass or fail line against the stated limit
  • Leak locations for any failed unit
  • A written report for your file

04Who and when

When a multifamily owner or developer needs the test

Who it is for

  • See New Construction.
  • General contractors managing the schedule on a stacked-unit project.
  • Owners of existing buildings who want a before and after measurement of an air-sealing project.

When you need it

  • Before drywall, if you want a chance to fix leaks cheaply. After drywall, the test shows the final result.
  • At the end of an air-sealing or retrofit phase.
  • When a program or building official asks for a test report.
  • When a resident reports drafts or smells from a neighbor's unit.
A hand holds an infrared camera, its screen showing a thermal image of a wall

In the field

An infrared camera shows where outside air is getting in.

An infrared camera, its screen showing a thermal image of a wall.

05Duct leakage testing

Duct leakage tests for the systems serving each unit

Where a unit has its own ducted heating and cooling system, leaky ducts waste air before it reaches the room. A duct test measures that loss. It can be done at the same visit as the blower door test.

  1. 01

    What the test measures

    We seal the supply and return openings, connect a fan and gauge to the duct system, and bring it to a set pressure. The fan flow needed to hold that pressure is the leakage.

  2. 02

    Total leakage and leakage to outside

    Total leakage counts every leak in the duct system. Leakage to outside counts only air that escapes to the outdoors. Your plans or program rules say which one applies.

  3. 03

    When it is done

    At rough-in, with the ducts exposed, leaks are easy to fix. At final, the test confirms the finished system. Some projects need both.

  4. 04

    Same visit as the air test

    A crew already in the unit with a blower door can often run the duct test at once, which saves a second trip and a second round of prep.

  5. 05

    When a system fails

    We point to likely leak locations. After the contractor seals them, we test again and report the new number.

  6. 06

    The limit and method

    The pass number comes from the code your jurisdiction adopted or from a program's rules. We do not quote one here.

06Questions

Questions we hear

Something else? Call 970-657-4197.

What is compartmentalization, and how is that test different?

Compartmentalization is how well each unit is sealed from neighboring units, halls and shafts. The test finds leakage that crosses shared walls and floors, which matters for smoke, odors, noise and comfort.

Guarded or unguarded blower door test: which one applies?

An unguarded test measures all leakage from a unit, including air from neighbors. A guarded test holds neighbors at the same pressure, so it isolates leakage to the outdoors. Your code or program says which one is required.

What does my city require, and what is the pass number?

It depends on the city or county. Fort Collins sets 0.27 cfm50 per square foot of unit enclosure area for stacked units. Other places differ, so we check the adopted code before we test.

How many units get tested, and what happens when one fails?

Fort Collins asks for seven units or 20 percent, whichever is greater, in buildings with eight or more units. In general we test about 10% of units on large buildings, with a sample of each unit type. Some programs need every unit tested at the same time. A failed unit is sealed and tested again. Ask the building department how a fail affects the rest of the sample.

When in construction should we test?

Many teams test before drywall when leaks are easy to reach, then test again at the end. Which test the building official counts depends on the jurisdiction.

Talk to us about your property

Tell us about the building or the portfolio, and what you need from it.

Monday to Friday, 8:00am to 5:00pm. Based in Fort Collins, Colorado.